The Plan Volume - Schedule Zone Set entity provides the schedule zone set that is assigned to a location in the workload set up.
Note: Because volume is created only for locations above Job in the Workload Planner, the Plan Volume - Schedule Zone Set entity can be used only for locations above Job (for example, Department) in Workload Planner.
Data Granularity
Provides one row per location above Job in the Business Structure.
A schedule zone set can contain multiple schedule zones that have been defined for a location. Schedule zones within the schedule zone set have exclusive start and end times. A schedule zone set cannot exceed 24 hours in length.